ELLABELL, Ga. (AP) — The steel skeletons of buildings where Hyundai will stamp, weld, paint and assemble electric vehicles in Georgia span more than a half mile on a sprawling site dotted with so many cranes, bulldozers and construction workers that it almost looks like they’re building a small city.
A year has passed since Hyundai Motor Group broke ground on the $7.6 billion vehicle and battery plant, the South Korean automaker’s first U.S. factory dedicated to producing EVs. Hyundai officials said more than 2,000 people are working each week on the rapidly progressing project west of Savannah, which the company calls its American “metaplant.”
“The site is advancing every day as we work diligently to complete this amazing project,” Hyundai Motor Group Metaplant America CEO Oscar Kwon told reporters visiting the site Wednesday. “We are on track to start production in early 2025 — or, as my boss Jose Munoz likes to say, if not sooner.”
Munoz, Hyundai’s president and global chief operating officer, said last month that the company has accelerated construction to take advantage of federal incentives that reward domestic production of EVs. He said it’s possible the plant could open before the end of next year.
Officials at the construction site Wednesday said the foundation work for the factory’s main production buildings is almost finished and the framework of more than 27,000 tons (24,490 metric tons) of steel is more than 80% complete. Some have roofs and floors, and exterior wall panels have begun to go up.
“It’s hard to believe what has occurred in just one year,” said Trip Tollison, president and CEO of the Savannah Area Economic Development Authority, one of the key local agencies that worked with state officials to lure Hyundai to Georgia.
The plant is being built parallel to Interstate 16 on a site that covers more than 2,900 acres (1,170 hectares). Hyundai says it will build 300,000 EVs each year at the plant. The site will also manufacture batteries to power those vehicles in a partnership between Hyundai and LG Energy Solution.
Hyundai offered a first look Wednesday at some features of the finished plant. Artist renderings showed buildings with plentiful windows and skylights to maximize natural lighting indoors, a large covered parking lot for employees topped with solar panels, and an elevated bridge with glass sides that will let people outside see unfinished cars moving by conveyor from the paint shop to the assembly plant.
The plant will employ 8,500 workers. Tollison said suppliers opening shop in nine Georgia counties near the Hyundai plant will create another 6,000 jobs.
It’s the largest economic development project in Georgia’s history. And it came with a whopping incentive package, with state officials and local governments offering $2.1 billion in tax breaks.
Pat Wilson, Georgia’s economic development commissioner, has said Hyundai is projected to have a direct payroll of $4.7 billion over the next 10 years. The company has promised to pay workers a yearly average of $58,105, plus benefits.
2024-12-24 09:511643 view
2024-12-24 09:262237 view
2024-12-24 09:052770 view
2024-12-24 08:452880 view
2024-12-24 08:292759 view
2024-12-24 07:532190 view
NEW YORK (AP) — Apologetic rapper Tekashi 6ix9ine was sentenced Tuesday to 45 days in prison by a fe
Is it nuts to assume a scoop of pistachio ice cream should contain actual pistachios? Or how about r
Although Lionel Messi said his 2022 World Cup run would be his last, Messi left the door open to pos